Kosmonte Foods
PV Truckport Kosovo: REPIC Pilot Project
Kosmonte Foods operates production and logistics sites in Kosovo, Albania, Germany, and the United Arab Emirates, and faces the challenge of supplying its growing fleet of electric commercial vehicles with clean energy. Ampere Dynamic is realising a PV Truckport with 200 kWp in its first phase together with local specialist Peak Valley L.L.C., as a REPIC-funded pilot project for development cooperation. The project draws on the technology of the award-winning Truckport at Hugelshofer Services AG in Switzerland, realised with partners, and transfers this approach to a South-East European market for the first time.
Construction has been under way since the fourth quarter of 2025. The truckport is built in two phases: 200 kWp in the first, followed by an expansion to around 0.5 MWp. The solar power generated on site feeds the charging infrastructure for Kosmonte Foods’ own fleet. The site sits on the main road corridor linking Kosovo to the markets of the Western Balkans.
Technology transfer from Switzerland to Kosovo is central to this project. Kosovo’s Energy Strategy 2022–2031 sets ambitious targets for expanding renewable energy. This pilot project makes a measurable contribution: on-site solar self-consumption, reduced dependence on the grid, and an electric charging infrastructure that enables the decarbonisation of logistics operations. As the first project of its kind in Kosovo, it carries flagship significance for the regional industry.
This is a joint undertaking between Ampere Dynamic Schweiz GmbH as EPC specialist, contributing Swiss planning and execution expertise, and Peak Valley L.L.C. as the local implementation partner, a Kosovar-Swiss joint venture with 150 MW of renewables in development. The project is financed through the REPIC platform, the Swiss interdepartmental funding instrument of SECO, DEZA, BAFU, and BFE for renewable energy in developing and transitioning countries. The next milestone is commissioning and the start of commercial operation.
Construction progress
-
November 2025: the solar modules arrive on site. -
December 2025: foundation works along the planted strips of the car park. -
December 2025: the first steel columns are up. -
January 2026: the canopy structure spreads across the car park. -
February 2026: steel framing in place over all three rows. -
February 2026: cantilevered beams at the end of a row. The same month, the installation crew was trained on site in the module mounting system. -
February 2026: the three canopy rows seen from the entrance. -
February 2026: the site on the main road corridor between Kosovo and the Western Balkans.
Project Timeline
Consultation & Concept
Q1–Q2 2025Feasibility study, site analysis and concept development for the PV Truckport at the Kosmonte site in Kosovo.
Engineering & Planning
Q3 2025Detailed design of the PV system, charging infrastructure and structural calculation of the Truckport structure.
Construction & Installation
since Q4 2025Setting out and foundations, steel columns and canopy structure over three rows, then mounting of the modules for the 200 kWp first phase and installation of the charging infrastructure.
Commissioning
next milestoneGrid connection, test operation and start of commercial charging operation.
Technical specifications
| Type | Photovoltaics, Infrastructure, Electrification |
|---|---|
| Mounting type | Truckport |
| Industry | Food Production and Logistics |
| PV capacity | 200 kWp |