Thinking Energy.
Delivering Solutions.

How We Built One of Europe's Largest E-Truck Charging Parks

Hugelshofer Services AG today operates one of Europe's largest e-truck fast-charging parks (as of 2024): 1'001 kWp, 28 charging points, 400 kW DC, winner of the Swiss Logistics Award 2024.

E-Mobility & Charging By Alexander Brendlin, Co-Founder & Managing Director

The Hugelshofer charging park is one of Europe's largest e-truck fast-charging parks (as of 2024): 28 charging points with up to 400 kW of DC power, supplied by a 1'001 kWp PV system on the truck port roof. 40% of the total charging energy comes from own solar production; the energy management system distributes the charging currents in real time and made a grid expansion to over 11 MW unnecessary. Ampere Dynamic delivered the project with partners; it received the Swiss Logistics Award 2024.

Key Takeaways

10 min read
  1. one of Europe's largest e-truck charging parks (as of 2024): a 1'001 kWp PV system combined with 28 charging points and 400 kW DC fast charging for 40-tonne trucks at one site.
  2. 40% of the total charging energy comes from own solar production. The project proves that high-performance charging infrastructure works without massive grid expansion.
  3. Swiss Logistics Award 2024: recognition for innovation in sustainable logistics infrastructure, the first e-truck charging park project of this scale in Europe.
  4. A replicable model: the three-layer architecture of rooftop PV, EMS and charging park transfers to any logistics business with 500 kWp of roof potential or more.
1'001 kWp
Installed solar capacity on the truck port roof
28 charging points
Of which 400 kW DC fast charging for 40-tonne trucks
40 %
Share of solar electricity in the total charging energy

The starting point: Hugelshofer’s challenge

Hugelshofer Logistik AG is an established Swiss transport company. When the company began to electrify its heavy-duty fleet step by step, it ran into a challenge many logistics businesses know: electric trucks need a lot of electricity, and they need it within a tight time window.

A modern 40-tonne truck needs several hundred kilowatt-hours for a full charge. Whoever wants to charge 28 such vehicles at the same time is talking about a simultaneous load that pushes even mid-sized industrial sites to their limits. At 400 kW of DC fast charging per station, the theoretical peak load exceeds 11 MW, a figure that would require massive and expensive grid expansion.

The second challenge: the truck port of the Hugelshofer logistics centre has a large unshaded roof area that until then had gone unused for energy. The potential was obvious. The question was how to link solar production, grid capacity and charging management intelligently.

The solution: three integrated systems as one concept

Ampere Dynamic delivered the project together with selected partners, from the feasibility study to commissioning. The solution rests on three layers that only deliver the intended performance together.

Layer 1: rooftop PV (1’001 kWp). The solar power plant on the truck port roof produces around 1’001 MWh of electricity per year. This own production supplies the charging park directly during the day, reduces grid draw and forms the economic basis of the entire system.

Layer 2: load and charging management system (EMS). The specially developed energy management system coordinates the charging currents of all 28 stations in real time: it takes into account current PV production, available grid capacity and the drivers’ route planning. When more solar electricity is available, charging power is raised. When less capacity is available, the EMS distributes the load dynamically to the stations with the lowest priority.

Layer 3: charging park (28 charging points at 400 kW DC). 14 fast-charging stations with two charging points each allow 28 e-trucks to charge simultaneously. DC fast charging at up to 400 kW per station allows a full charge of a 40-tonne truck in around 90 minutes.

The decisive point: none of these systems works without the other two. Without the EMS, the simultaneous load of several 400 kW stations would destabilise the grid. Without PV, the economics of the system would collapse. And without the charging park there would be no sensible consumer for the solar energy produced.

More on the integrated planning of charging infrastructure and PV: Solar systems for logistics centres. Ampere Dynamic’s complete offering for fleet operators is described on the logistics electrification solution page.

Technical details: the solar power plant

The heart of the system is 2’314 solar modules on 1’283 m² of truck port roof. The total capacity is 1’001 kWp with a forecast annual production of around 1’001 MWh.

The truck port proved to be the ideal mounting location. The reasons:

  • Unshaded large area: The truck port’s flat roof is open and clear of obstructing structures. The modules can be mounted in optimal orientation and without shading one another.
  • Structural capacity: Modern industrial flat roofs are designed for snow load. The weight of the PV system is well below that. No structural reinforcement was necessary.
  • Short cable runs: The charging park sits directly beneath the truck port roof. The proximity between PV system and consumers minimises DC cable losses and considerably simplifies the system architecture.
  • Grid connection: A purpose-built transformer station secures the medium-voltage connection to cover peak loads outside solar production hours.

The load and charging management system

The EMS is the intelligent heart of the installation. It solves the fundamental problem of every large charging park: how do you charge many vehicles at once without overloading the grid and without giving up on route planning?

Hugelshofer’s system coordinates three inputs in real time: the solar power plant’s current PV production, the available grid capacity under the agreed connection tariff, and each vehicle’s charging priority based on route planning.

The result: 40% of the total charging energy comes from own PV production. The remaining 60% the vehicles draw from the grid, but evenly distributed and within the agreed connection capacity. A cost-intensive grid expansion to 11+ MW was not needed.

For logistics businesses planning their charging infrastructure, we recommend the guide Charging infrastructure for businesses.

What other logistics businesses can learn from Hugelshofer

The Hugelshofer project is not a one-off but a model. The three-layer architecture of rooftop PV, EMS and charging park transfers to any logistics business with sufficient roof area and a growing electric fleet.

Lesson 1: integrated planning from the start. Whoever builds the charging park first and retrofits the PV system loses the economic synergies. Grid connection, transformer capacity, PV design and EMS configuration must be aligned before the first ground-breaking.

Lesson 2: PV as the economic basis. A pure charging park without own generation is expensive to operate. The 40% solar electricity at Hugelshofer measurably reduces operating costs and secures the economics as grid electricity prices rise.

Lesson 3: the EMS as the precondition for high-power charging. Without intelligent charging management, simultaneous 400 kW charging of many vehicles is not feasible on the grid, at least not without prohibitively expensive connection capacity. The EMS enables high charging power within existing grid capacity limits.

Lesson 4: phased expansion is possible. The infrastructure (cable routes, transformer station, basic EMS configuration) can be designed for more charging points from the start. Charging stations can then be added as the fleet grows.

A complete overview of the specifics of logistics centres is in the article Solar systems for logistics centres.

Subsidies for e-truck charging infrastructure

For logistics businesses planning similar projects, three subsidy programmes are available.

GREIV (the one-off payment) supports the PV component with up to 30% of the eligible investment costs. The subsidy applies regardless of company size and can be planned on.

The ASTAG sector programme is aimed at SMEs with fewer than 250 employees and supports e-truck charging infrastructure with up to 40% of the eligible costs. The programme runs until the end of 2027 (budget CHF 20 million). Applications must be submitted before construction starts.

KlG (Climate and Innovation Act) applies to businesses from 250 employees with a net-zero roadmap and supports up to 50% of the investment costs.

A complete overview of all subsidy programmes is in the Subsidy Guide 2026.

Project phases: from concept to one of one of Europe's largest e-truck charging parks (as of 2024)s

Concept & feasibility study

Demand analysis for the charging infrastructure, load profile of the growing e-truck fleet, structural check of the truck port roof, grid connection review and economic simulation of the integrated overall system.

  • Duration: 4-6 weeks

Planning & permits

Building permit for charging park and PV system, GREIV subsidy application, grid connection application to the local grid operator, tender for the transformer station.

  • Duration: 3-4 months

Civil works & infrastructure

Civil engineering for cable routes, construction of the transformer station, foundations for the charging park, earthing and protective conductor installation.

  • Duration: 3-4 months

PV installation & electrical

Mounting of the 2'314 modules on 1'283 m² of truck port roof, installation of the inverters, DC cabling, connection to the medium-voltage grid.

  • Duration: 2-3 months

Commissioning & EMS configuration

Configuration of the charging management software, dynamic load distribution across 28 charging points, monitoring connection, link to route planning.

  • Duration: 4-6 weeks